|
Changes...the
Range of Proposed Improvements to Michigan's Wetland
Protection Program
By Chris Grubb
In 1984
Michigan became the first state, and is currently
one of only two states, authorized to administer
the Section 404 (wetlands protection) permitting
program of the Clean Water Act. To maintain authority
for the Section 404 Program, a state must show that
its program is at least as protective as the federal
Section 404 Program. In early 1998 the U.S. Environmental
Protection Agency (EPA) began an informal but comprehensive
review of Michigan’s Section 404 Program because
a number of relevant state and federal statutes
had changed since 1984. A body of Michigan judicial
and administrative opinions had developed relevant
to the program; and, they had received many complaints
about the administration of the program. The results
of this review were presented to the Michigan Department
of Environmental Quality (MDEQ) and published in
the Federal Register for public review and comment
in March, 2003. MDEQ has responded by proposing
to take the following actions to address the concerns
raised in EPA’s review:
Administrative
Actions
Isolated wetlands greater than five acres are protected
by Michigan’s Wetland Protection law, but in counties
having less than 100,000 people MDEQ needs to conduct
an inventory process to gain jurisdiction. This
inventory process is underway and the department
proposes to complete the inventory by 2006. Isolated
wetlands less than five acres in size are only protected
if the department finds the protection of the area
is essential to the preservation of the natural
resources of the state. The agency will also work
with EPA to ensure that permit conditions required
by EPA’s administrative rules are incorporated into
the permits they issue. Federally listed threatened
and endangered species will also be taken into closer
consideration by working with EPA and U.S. Fish
and Wildlife Service to improve screening for permit
applications thatmay impact these species. MDEQ
has also agreed to issue public notice for any Proposal
for Decision that would have more impact on natural
resources than the permit application, and to develop
a procedure to notify adjacent states of permit
applications that would impact waters of those states.
Revised
Rules for Inland Lakes & Streams (Part 301)
and Wetlands (Part 303)
Under Part 301, MDEQ will seek to revise administrative
rules to limit the definition of the exemption for
drain “maintenance and improvement” to be consistent
with the federal definition. The agency will seek
to revise administrative rules to consider cumulative
impacts when new minor permit categories are established,
limit the term of permits to five years, authorize
modification of permits and add grounds for revocation
of permits, and require staff to consider impacts
to threatened and endangered species during the
review process. Under Part 303, the agency will
seek to revise administrative rules to incorporate
several of the issues above, amend the evaluation
of feasible and prudent alternatives to comply with
federal regulation, and clarify the exemption for
road maintenance.
Legislative
Actions
Legislatively, the MDEQ will be seeking several
amendments to Part 303 to ensure consistency with
Section 404 of the federal Clean Water Act. The
agency will seek to clarify the wetland inventory
process to gain jurisdiction over all wetlands that
are larger than five acres and not connected to
other wetlands. Also, MDEQ will be looking to alter
exemptions for agricultural and forestry activities,
agricultural drainage, drain maintenance, certain
utilities, and iron and copper mining tailings basins.
Issuance
of Opinions by Attorney General
As new administrative rules are adopted, MDEQ will
seek to provide written opinion from the Michigan
Attorney General addressing the applicability of
the new rules to pending permit applications and
contested cases. The Department of the Attorney
General has also agreed to provide a final statement
indicating Michigan’s legal authority to continue
administering the Section 404 Program.
Revising
the Section 404 Program Memorandum of Agreement
The current Memorandum of Agreement (MOA) between
EPA and MDEQ is out of date, and will need to be
revised. The updated MOA will reflect changes in
enforcement procedures, and will clarify that any
permit issued because MDEQ exceeded the 90-day limit
for permit review will be a state-only (not federal)
permit. MDEQ has also requested that a MOA between
the agency and the Army Corps of Engineers be modified
to clearly define the Corps' jurisdiction for wetlands
occurring on Native American lands.
Conclusion
Michigan has long been seen as a leader in wetland
protection. Due to changes in both state and federal
law in the 1990s, Michigan must make some positive
changes to regain its mantle of wetland leader.
Given the importance of wetlands, and Michigan’s
place in the center of the Great Lakes, it is important
that citizens work with the MDEQ to bring about
these changes.
|